Aquarion Road Work Update, July 1, 2026

Starting June 15, 2026, Aquarion will be working on New Canaan Road (Rte. 106) between Old Boston Road and Katydid Lane.
- Week of June 15- Removal of nine (9) inches of asphalt.
- Week of June 22nd -Paving (7-inches of asphalt).
Tentative Schedule:
Starting June 29th, 2026, Aquarion will be working on New Canaan Road (Rte. 106) between Katydid Lane and Trails End Road, Wilton CT.
- Week of June 29th - Removal of nine (9) inches of asphalt.
- Week of July 6th -Paving (7-inches of asphalt).
Tentative Schedule:
Starting June 29 Work between Trails End Road and Old Kings Highway, Wilton CT.
- Week of July 13th - Removal of nine (9) inches of asphalt.
- Week of July 20th -Paving (7-inches of asphalt).
Upon completion of the work outlined above, the contractor will communicate the schedule for placement of the final 2-inch asphalt surface course.
The timelines above are estimate of duration of work and is weather dependent. Modifications to the above schedule will be communicated via AWC & Towns of Wilton and New Canaan Websites.
Please follow the detour route shown on the attached sheet during construction hours. The detour route consists of Old Boston Road and Old Kings Highway.
Normal Construction hours will be from 7am to 5:30pm. However, to encourage a timelier completion of the project in our neighborhoods, construction hours may be adjusted from 7am-5:30pm to 7am-7pm. In special circumstances Saturday work may be required.
Residents living in project area above please allow extra time to enter/exit the respective work zones and please coordinate with traffic control for access to your property. All bus stops will remain at their current locations. Emergency vehicles will be granted immediate access through the work area.
The State of Connecticut is overseeing the project. If you have questions about the project, please call:
Dennis Fields, Aquarion Water project representative, 203-258-6139 or
Joseph Sorcinelli, CT DOT Project Engineer, 203-389-3162
Ken Zembrzuski, Eversource Project Representative, 860-665-3452.
For additional project information, please visit the Aquarion website: Southwest Regional Pipeline Transmission Water Main - Wilton & New Canaan | Aquarion Water